Utilities
PERMITTING ISSUES
Utilities located in the county road right-of-way require approval
through a permitting process. The county Utility Road Crossing Inspector
will assist in ensuring county regulations are met in order to issue
a permit. The compliance will cover right-of-way obstruction, diversion
of water, and damage to the county road.
There is an application fee for a Utility Road Crossing Permit as
required by Title
4 – Construction within Public ROW or Across County Road Order.
Get
Utility Road Crossing Cross Section |
 |
|
PERMITTING PROCESS
Generally, the permitting process goes as follows:
- Submit an application to the Comal County Engineer's Office
(CCEO) along with the permit fee
- The Utility Road Crossing Inspector will arrange to meet the
applicant on site to finalize the application
- The Utility Road Crossing Inspector will issue a Permit to Construct
- When construction is complete, the applicant will contact CCEO
- The Utility Road Crossing Inspector will perform the final inspection
- The Comal County Engineer's Office will issue the Utility Road
Crossing Permit
- For an appointment, call: (830) 221-8035 or (830) 608-2090
- Most often a permit is issued upon completion of the inspection
Get
Utility Road Crossing Permit Application |
| |
|